"Public trust depends on our ability to show progress in years, not in decades," Metro board member Katy Yaroslavsky said on January 22, 2026, according to the Los Angeles Times. That was the day the board unanimously chose a route for the Sepulveda Transit Corridor. Ten months later, Metro has published a route and a station list for the Valley but no schedule for building them.
If you're weighing Sherman Oaks against other Valley neighborhoods, those two facts deserve different weight. Metro plans a Sherman Oaks station at or near Ventura and Van Nuys, and that stop is part of both the full line and the shorter first segment the board named. The opening date isn't known, and that shouldn't drive a purchase. In between sits one decision still being made a short drive from Ventura Boulevard: where Metro stores and repairs its trains.
The route Metro picked
The plan the board adopted, called Modified Alternative 5, is about 12.3 miles of automated heavy rail in a single-bore tunnel. All seven stations are underground. In the Valley it runs under Van Nuys Boulevard, and the Sherman Oaks stop is listed as Ventura/Van Nuys. Metro's spring 2026 fact sheet says the adopted plan has no aerial track along Sepulveda Boulevard in the Valley.
That closed off the version Sherman Oaks residents had worried about most. The Sherman Oaks Homeowners Association credits Bob Anderson, its transportation committee chair, with helping keep elevated trains off Sepulveda. After the vote, Anderson told the Los Angeles Times he was "pleasantly surprised" that Metro had listened to residents. The paper reported that the Van Nuys Boulevard route came about after concerns over drilling near a high-pressure water main along Sepulveda.
The time savings Metro projects show why the line exists. According to its November 2026 scoping presentation, the trip from Van Nuys Metrolink to the E Line would take under 20 minutes, compared with 40 to 80 minutes by car today. If you already know the Sepulveda Pass on a bad weekend, the 405 repaving weekends around Sherman Oaks is the everyday version of the problem.
Why the first segment matters for Sherman Oaks
The station's location carries real weight because of how Metro plans to build the line. Along with the full route, the board named an Initial Operating Segment: about 8.4 miles from the G Line in Van Nuys to Wilshire/Westwood on the D Line, with four underground stations. Those four are Wilshire/Westwood, UCLA, Ventura/Van Nuys and G Line/Van Nuys, and Metro puts the ride from the G Line to the D Line at about ten minutes.
Ventura/Van Nuys is in that first segment. The Van Nuys Metrolink and Expo/Sepulveda stations are not. Metro's FAQ says its funding strategy focuses on constructing the first segment first. Of the Valley's three planned stops, the Sherman Oaks stop is one of the two included in both the first segment and the full line.
SOHA reads the phasing with some skepticism. In an October 2026 item on the association's transit page, Anderson wrote that the first segment gives the Valley two stations where three or four had been promised. That concern is about the stations north of the G Line. If you're focused on Ventura Boulevard, the same detail points the other way: Ventura/Van Nuys is in the first piece Metro plans to build.
The yard decision
Every rail line needs a maintenance and storage facility near its tracks, where trains are parked, cleaned and repaired and where crews report to work. The yard sites studied in the 2025 Draft EIR were outside the first segment, so Metro is looking at five new options:
- The existing Westfield Fashion Square on Riverside Drive
- Along Oxnard Street between Kester Avenue and Sepulveda Boulevard
- Existing Metro parking and adjacent properties near the G Line Van Nuys station
- North of Victory Boulevard, immediately west of Van Nuys Boulevard
- The Plant shopping center and adjacent properties east of Van Nuys Boulevard
Option 1 matters most for Sherman Oaks, and the same slide deck explains why it is a live candidate. Metro's chart shows Options 1 and 2 as the only sites that could serve the first segment and then expand for the full line. Options 3 and 4 would each need The Plant added as a second site once the line is complete. Metro notes on every one of these slides that site locations, sizes and layouts will be refined as design progresses.
For now, Fashion Square is a working mall. Unibail-Rodamco-Westfield's portfolio page still lists it, with an acquisition year of 2002 and a last refurbishment in 2012. The Westfield directory lists Macy's and Bloomingdale's. SOHA's comings and goings column reported BoxUnion as a new addition in June 2026. In October it described the mall's exterior row of Noodle St, Kura Revolving Sushi Bar, Panini Kabob Grill, BoxUnion and Orangetheory Fitness as active and said Noodle St was drawing crowds.
SOHA has come out against putting the yard in the neighborhood. Its November 2026 post asks residents to help stop Metro from building the facility in Sherman Oaks and warns that it could take Fashion Square or another local site. Across the Valley, the Greater Valley Glen Council has posted the full list of five sites and invited residents to weigh in.
Metro's project page lists comments due November 23, 2026. Comments can go through its online form, by email to [email protected], or by phone at 213.922.7375. Metro's FAQ says the Recirculated Draft EIR, which will study the new yard location, is expected in 2027. That document is when the yard question narrows. It is also the next milestone to watch if you're thinking about buying near Riverside Drive or along Oxnard Street.
The calendar has no end date yet
The best way to judge the opening date is to look at what has been funded and scheduled so far. As of the January vote, the Los Angeles Times reported that roughly $3.5 billion had been secured through Measure M and Measure R. Metro had no cost estimate for the modified route, and the earlier figure of about $24.2 billion did not apply to it. The paper also reported that a mid-2038 opening date belonged to a previous version of the route, with no updated schedule for the new one.
Metro's spring 2026 fact sheet says the Measure M spending plan identifies $5.7 billion for the project and expects more federal, state, local and possibly private money. It describes a public-private partnership as something the agency is still "further assessing." The project page still lists the phase as Planning and says an updated construction timeline will be shared when it's available. SOHA says California Public Records Act requests showed design work running until March 2027 and environmental work until the end of 2028.
Those dates describe planning, not construction. If you buy a home in Sherman Oaks in 2026, the line is something you'll follow through several more rounds of public review before any tunneling starts. Councilmember Nithya Raman's District 4 page describes Metro as refining the plan, evaluating phasing and further assessing that partnership model.
What's moving near Ventura and Van Nuys now
The station isn't the only change planned near that intersection. In December 2025, Urbanize LA reported an application for a six-story affordable building at 14318 W. Dickens Street, with 75 one- and two-bedroom apartments in place of five homes. In January 2026, Urbanize LA covered a plan to replace a two-story preschool building at 4276 N. Van Nuys Boulevard with eight small-lot homes, each with room for an ADU. The city's planning case page lists that application, filed December 19, 2025, as on hold.
Both are proposals, and neither depends on a train that has no opening date. Together they show the kinds of projects already being filed in the station area, and they give you something to look up when a listing nearby mentions transit. On the boulevard itself, Eater LA reported that Mistral at 13422 Ventura Boulevard reopened in August 2026 under new operators Jonah Freedman and Josh Migdal. That stretch of Ventura has been changing hands with its old uses intact.
Using the line in a home search
Base your comparison on facts you can check this week. Metro has published the station location, the underground route and the five yard sites. When you compare a home a few blocks from Van Nuys Boulevard with one across the Valley, you can measure the distance to Ventura/Van Nuys today and watch the 2027 environmental document for refined station designs. The opening year is still unknown. The yard site is the one decision likely to narrow during an ordinary ownership period, and Metro has said the 2027 environmental document will take it up.
The Sherman Oaks neighborhood page covers the parts of the neighborhood that have nothing to do with rail.
A few quick answers
Will trains run above Van Nuys or Sepulveda Boulevard in Sherman Oaks? Metro's adopted plan is underground for its full length, and its fact sheet says there is no aerial alignment along Sepulveda in the Valley.
Has Metro chosen Fashion Square for the train yard? No. It is Option 1 of five sites Metro will study, and Metro says site locations, sizes and layouts will be refined as design progresses.
When could the Sherman Oaks station open? Metro hasn't published an updated construction timeline for the adopted route.
If you're weighing a home near Van Nuys Boulevard, Riverside Drive or Oxnard Street and want help tracking what Metro's 2027 document could mean for a specific street, Cindi Brodack is glad to go through the maps with you and help you build a timeline you can plan around. Let's Connect.